An OECP card lasts five years. To renew it you pass a 50-question written for each crane type on your card, and the practical is waived if you have the hours. Use these 20 questions to find out what has slipped since your last exam.

What these practice questions cover

  • OSHA 1926 Subpart CC
  • ASME B30.5
  • Power line clearances
  • Inspections and wire rope
  • Personnel platforms
  • Operational aids
OECP crane recertification at a glance
Written exam50 questions for each crane type on your card
Practical examWaived with 1,000 documented hours on that crane type during the certification period, worked for a signatory contractor or employer
When to startAt least six months before your card expires
Time it takesA few hours if the practical is waived. Plan a full day if it is not
Card life5 years

Sources: OECP FAQ and OECP recertification eligibility. Checked November 2026.

20 recertification practice questions

Pick an answer to see if you are right and why. These are original practice questions from the Crane Exam Prep question bank, not actual OECP exam questions.

  1. OSHA 1926 Subpart CC

    1. According to OSHA 1926.1431, hooks used in the connection between the hoist line and the personnel platform must be:

    Show answer

    Answer: D. Of a type that can be closed and locked, eliminating the throat opening, and closed and locked when attached. 1926.1431(g)(1)(i) requires closed-and-locked hooks eliminating the throat opening; shackles used in place of hooks must be alloy anchor type with bolt/nut/retaining pin or secured screw pin.

  2. ASME B30.5 (Mobile Cranes)

    2. According to ASME B30.5, an anti-two-block device is one that, when activated:

    Show answer

    Answer: C. Disengages all functions whose movement can cause two-blocking. The anti-two-block device disengages all crane functions whose movement can cause two-blocking; a two-block warning feature only alerts the operator.

  3. Inspections

    3. At the start of each shift, before handling a load, the operator should function-test…

    Show answer

    Answer: B. The operating controls and the limiting/warning devices. A start-of-shift function test confirms the controls and limit/warning devices — such as the anti-two-block — operate before load handling begins.

  4. Standards

    4. OSHA 1926.1419 through 1926.1422 address which topic?

    Show answer

    Answer: B. Signals — hand, voice, audible, and new. Sections 1926.1419-1422 of Subpart CC cover hand, voice, audible, and new signals.

  5. Standards & Violations

    5. Swinging into a load or dragging it sideways is prohibited because it…

    Show answer

    Answer: D. Side-loads the boom, which is designed for compression, not sideways force. Booms take enormous vertical load and very little side load — side loading buckles booms. Boom tip over the load, hoist line plumb.

  6. Wire Rope

    6. A wire rope must be removed when the outside wires are worn away by what fraction of their original diameter?

    Show answer

    Answer: B. One-third. Removal is required when individual outside wires are worn to one-third of their original diameter, indicating serious abrasion loss.

  7. Power Lines

    7. During power-line encroachment work, who is permitted in the area of the crane and load?

    Show answer

    Answer: A. Only personnel essential to the operation. Only personnel essential to the operation may be in the area of the crane and load during power-line work.

  8. Operations

    8. A personnel platform must be designed to support its own weight plus at least how many times the intended load?

    Show answer

    Answer: C. 5 times. OSHA and ASME B30.23 require the platform to hold its own weight and at least five times the intended load.

  9. Site Setup

    9. As a level check, the boom is raised to its highest angle and the whip line lowered with a small compact load. If the crane is 1% off level with the boom tip 100 feet high, roughly how far off centre will the line hang?

    Show answer

    Answer: A. About 12 inches. The hanging line acts as a plumb bob: 1% of a 100 foot height is about one foot of offset. Checked in every quadrant, the line should hang dead centre on the boom.

  10. OSHA 1926 Subpart CC

    10. According to OSHA 1926.1437, the internal portion of a barge or vessel supporting a crane must be surveyed by a marine engineer, marine architect, licensed surveyor, or other qualified person with vessel expertise every:

    Show answer

    Answer: A. Four years. 1926.1437(h)(5) requires a four-year internal vessel/flotation device inspection; its documentation must be retained for a minimum of 4 years.

  11. ASME B30.5 (Mobile Cranes)

    11. According to ASME B30.5, side loading of booms shall be limited to:

    Show answer

    Answer: A. Freely suspended loads. Para 5-3.2.1.5(d) limits side loading of booms to freely suspended loads and prohibits using cranes for dragging loads sideways.

  12. Inspections

    12. Cold-weather operation adds inspection attention to…

    Show answer

    Answer: D. Ice accumulation on wire rope, sheaves, brakes, and controls. In freezing conditions the competent person watches for ice on ropes, sheaves, brakes, and controls that can impair safe operation.

  13. Standards

    13. Pick-and-carry operations near power lines must comply with which OSHA sections?

    Show answer

    Answer: C. 1926.1408 and 1926.1409. Because the crane is loaded, pick-and-carry work near power lines falls under 1926.1408 and 1926.1409 rather than the unloaded-travel section.

  14. Standards & Violations

    14. Running the crane with a bypassed anti-two-block or LMI violates…

    Show answer

    Answer: B. OSHA 1926.1416. 1926.1416 covers operational aids. When one fails, the regulation allows only limited temporary alternatives — otherwise out of service.

  15. Wire Rope

    15. During an internal rope examination of a fiber core rope, what do short pieces of fiber less than 1/4 inch long sifting out of the core indicate?

    Show answer

    Answer: D. The core is breaking up, often from overloading, tight sheaves, or other abuse. Short broken fibers under 1/4 inch indicate the core is breaking up, suggesting overloading, pinching in tight sheaves, or abuse.

  16. Power Lines

    16. When working near an energized overhead power line rated up to 50 kV, what is the minimum clearance that must be maintained between the crane (including load and rigging) and the line under OSHA 1926 Subpart CC?

    Show answer

    Answer: C. 10 feet. For lines up to 50 kV, the minimum approach distance is 10 ft. Clearance increases for higher voltages.

  17. Operations

    17. When a heavy load first lifts off the ground, expect it to…

    Show answer

    Answer: B. Swing out away from the crane. Boom deflection makes the load drift outward — pre-set your boom angle higher to compensate.

  18. Site Setup

    18. Before loading the outriggers you should…

    Show answer

    Answer: C. Extend per the chart and set pads or cribbing. Outriggers need full extension per the chart and solid support under every pad.

  19. OSHA 1926 Subpart CC

    19. According to OSHA 1926.1407, assembly or disassembly of a crane below a power line is:

    Show answer

    Answer: C. Prohibited unless the utility owner/operator has deenergized and visibly grounded the line at the worksite. 1926.1407(c) prohibits any part of a crane, load line, or load below a power line unless it has been confirmed deenergized and visibly grounded at the worksite.

  20. ASME B30.5 (Mobile Cranes)

    20. According to ASME B30.5, a 'dedicated spotter' is a qualified signalperson whose sole responsibility is to:

    Show answer

    Answer: D. Verify that the specified clearance is maintained. A dedicated spotter is in continuous contact with the operator and has the sole responsibility of verifying that the specified clearance (from power lines) is maintained.

FAQ

Common questions

How many questions are on the OECP recertification exam?
Recertification requires passing a 50-question written exam for each crane type on your card.
Do I have to retake the practical to recertify?
Not if you have at least 1,000 hours of documented safe operating experience on that crane type during the certification period. OECP requires that experience to be with a signatory contractor or employer.
When should I start recertification?
OECP says to start at least six months before your card expires.
How is Signal Person Rigger recertification different?
Signal Person Rigger recertification is a 110-question written exam. The candidate manual lists no practical for recertification.
Are these the real OECP exam questions?
No. OECP does not release its questions and does not supply study material. These are original practice questions written from the OSHA crane rules and ASME B30 standards. This site is not affiliated with OECP or the IUOE.

More OECP practice tests

Keep studying in the full app.

5,000+ questions, lessons and a readiness score. Free to start.

Create a free account
More recertification questionsFree account, no card
Open the app