25 questions
OECP practice test
The mixed mobile crane test.
Take the 25-question testFree, no sign-up
An OECP card lasts five years. To renew it you pass a 50-question written for each crane type on your card, and the practical is waived if you have the hours. Use these 20 questions to find out what has slipped since your last exam.
| Written exam | 50 questions for each crane type on your card |
|---|---|
| Practical exam | Waived with 1,000 documented hours on that crane type during the certification period, worked for a signatory contractor or employer |
| When to start | At least six months before your card expires |
| Time it takes | A few hours if the practical is waived. Plan a full day if it is not |
| Card life | 5 years |
Sources: OECP FAQ and OECP recertification eligibility. Checked November 2026.
Pick an answer to see if you are right and why. These are original practice questions from the Crane Exam Prep question bank, not actual OECP exam questions.
Answer: D. Of a type that can be closed and locked, eliminating the throat opening, and closed and locked when attached. 1926.1431(g)(1)(i) requires closed-and-locked hooks eliminating the throat opening; shackles used in place of hooks must be alloy anchor type with bolt/nut/retaining pin or secured screw pin.
Answer: C. Disengages all functions whose movement can cause two-blocking. The anti-two-block device disengages all crane functions whose movement can cause two-blocking; a two-block warning feature only alerts the operator.
Answer: B. The operating controls and the limiting/warning devices. A start-of-shift function test confirms the controls and limit/warning devices — such as the anti-two-block — operate before load handling begins.
Answer: B. Signals — hand, voice, audible, and new. Sections 1926.1419-1422 of Subpart CC cover hand, voice, audible, and new signals.
Answer: D. Side-loads the boom, which is designed for compression, not sideways force. Booms take enormous vertical load and very little side load — side loading buckles booms. Boom tip over the load, hoist line plumb.
Answer: B. One-third. Removal is required when individual outside wires are worn to one-third of their original diameter, indicating serious abrasion loss.
Answer: A. Only personnel essential to the operation. Only personnel essential to the operation may be in the area of the crane and load during power-line work.
Answer: C. 5 times. OSHA and ASME B30.23 require the platform to hold its own weight and at least five times the intended load.
Answer: A. About 12 inches. The hanging line acts as a plumb bob: 1% of a 100 foot height is about one foot of offset. Checked in every quadrant, the line should hang dead centre on the boom.
Answer: A. Four years. 1926.1437(h)(5) requires a four-year internal vessel/flotation device inspection; its documentation must be retained for a minimum of 4 years.
Answer: A. Freely suspended loads. Para 5-3.2.1.5(d) limits side loading of booms to freely suspended loads and prohibits using cranes for dragging loads sideways.
Answer: D. Ice accumulation on wire rope, sheaves, brakes, and controls. In freezing conditions the competent person watches for ice on ropes, sheaves, brakes, and controls that can impair safe operation.
Answer: C. 1926.1408 and 1926.1409. Because the crane is loaded, pick-and-carry work near power lines falls under 1926.1408 and 1926.1409 rather than the unloaded-travel section.
Answer: B. OSHA 1926.1416. 1926.1416 covers operational aids. When one fails, the regulation allows only limited temporary alternatives — otherwise out of service.
Answer: D. The core is breaking up, often from overloading, tight sheaves, or other abuse. Short broken fibers under 1/4 inch indicate the core is breaking up, suggesting overloading, pinching in tight sheaves, or abuse.
Answer: C. 10 feet. For lines up to 50 kV, the minimum approach distance is 10 ft. Clearance increases for higher voltages.
Answer: B. Swing out away from the crane. Boom deflection makes the load drift outward — pre-set your boom angle higher to compensate.
Answer: C. Extend per the chart and set pads or cribbing. Outriggers need full extension per the chart and solid support under every pad.
Answer: C. Prohibited unless the utility owner/operator has deenergized and visibly grounded the line at the worksite. 1926.1407(c) prohibits any part of a crane, load line, or load below a power line unless it has been confirmed deenergized and visibly grounded at the worksite.
Answer: D. Verify that the specified clearance is maintained. A dedicated spotter is in continuous contact with the operator and has the sole responsibility of verifying that the specified clearance (from power lines) is maintained.
Your result
FAQ
25 questions
The mixed mobile crane test.
Take the 25-question test75 questions
One written exam for boom truck, lattice boom and telescopic boom.
Mobile crane practice test75 questions
Its own written exam, including self-erecting tower cranes.
Tower crane practice test75 questions
Its own written exam for overhead crane operators.
Overhead crane practice test5,000+ questions, lessons and a readiness score. Free to start.