Tower crane operators take their own OECP written exam: 75 multiple-choice questions in two hours. To be eligible, 500 of your 1,000 documented hours must be on tower cranes. Try 20 free tower crane questions below.
| Questions | 75 multiple choice |
|---|---|
| Time limit | 2 hours |
| Passing score | Scaled score of 500 on a 200 to 800 scale |
| Crane types covered | Tower cranes, including portable and self-erecting types |
| Experience needed | 1,000 documented hours in the past five years, 500 of them on tower cranes |
| Calculators | Not allowed |
| After you pass | A hands-on tower crane practical exam |
Sources: OECP Crane Operator Candidate Manual, OECP initial certification eligibility and OECP FAQ. Checked November 2026.
Pick an answer to see if you are right and why. These are original practice questions from the Crane Exam Prep question bank, not actual OECP exam questions.
Answer: B. Only with the hoist gear at a standstill. The operating instructions require gear shifting to be performed only with the hoist gear stopped.
Answer: D. Adding tower sections at the top. Climbing increases height by adding tower sections at the top; internal climbing cranes are instead raised within the structure.
Answer: D. The maximum velocity recommended by the manufacturer. Cranes shall not be operated when wind speeds exceed the maximum velocity recommended by the manufacturer.
Answer: D. Operator. ASME B30.3 3-3.1.3(n): the operator must be present during climbing/telescoping.
Answer: B. Construction tower cranes and permanently mounted tower cranes. B30.3 applies to construction tower cranes and permanently mounted tower cranes powered by electric motors or internal combustion engines; self-erectors (B30.29) and mobile crane tower attachments (B30.5) are excluded.
Answer: D. The crane is completely erected. Bolts should not be tensioned to provide full pre-stress until the crane is completely erected (3-1.1.2(e)).
Answer: B. Shock absorbing, with a jib hoist limit switch also required on luffing cranes. Shock-absorbing stops keep the jib from slamming, and on luffing machines a jib hoist limit switch stops the jib before it reaches the stop at all.
Answer: A. Slack rope can spool loosely or incorrectly onto the drum. If the block is lowered to the ground the hoist line must not be allowed to go slack, because slack rope spools loosely or incorrectly onto the drum.
Answer: A. 10 ABC. ASME B30.3 3-1.23.4: a class 10 ABC fire extinguisher in the cab/machinery platform.
Answer: B. Roughly doubles. Going from 1-part to 2-part reeving roughly doubles the maximum rated load, though it halves line speed.
Answer: A. At a 5% overload, regardless of the jib or trolley position. The hoist line overload switch cuts hoisting power at a 5% overload no matter where the jib or trolley is positioned.
Answer: C. 5.0 to 1. ASME B30.3 3-1.10.5(b): rotation resistant load hoist wire rope design factor = 5.0 to 1.
Answer: B. Rail mounted. Rail-mounted tower cranes run on engineered track and can accept any tower or jib configuration, so they travel under load better than a comparable mobile tower crane.
Answer: D. Lower it to the uppermost tie-in assembly. The manufacturer requires the top climbing unit to be lowered to the uppermost tie-in before the crane operates at its maximum tower configuration.
Answer: B. Because a tower crane must not be tested at more than 5% overload, unlike the 125% used for many crane types. Many crane types are proof-tested at 125% of rated capacity, but a tower crane must not be tested at more than a 5% overload.
Answer: D. 18 times. Load block sheave pitch diameters shall be not less than 18 times the nominal rope diameter; luffing boom hoist sheaves not less than 15 times.
Answer: C. At or near the top of the crane. A wind velocity measuring device shall be mounted at or near the top of the crane, with a readout in the cab.
Answer: A. The float pads alone are too small to spread reaction loads and prevent settlement. Outrigger reactions are substantial, and the float pads lack the area to spread them, so a qualified person sizes footings or mats using the soil report and the maximum reactions from the manufacturer.
Answer: C. EN 14439, Section 5.2. B30.3 requires strength and stability of load-bearing structures to be calculated in accordance with EN 14439:2006+A2, Section 5.2.
Answer: A. Moving the trolley in or out along the jib to change the load radius. Trolleying is the radius-change motion on a hammerhead crane, moving the trolley along the horizontal jib.
Your result
FAQ
25 questions
The mixed mobile crane test.
Take the 25-question test75 questions
One written exam for boom truck, lattice boom and telescopic boom.
Mobile crane practice test75 questions
Its own written exam for overhead crane operators.
Overhead crane practice test110 questions
One OECP certification for signaling and rigging together.
Signal person rigger practice test5,000+ questions, lessons and a readiness score. Free to start.