Operating engineers practice test

Operating engineers face two different kinds of test. One gets you into the apprenticeship. The other certifies you to run a crane. The 15 free questions below are the second kind: crane setup, operation, rigging and inspections.

The short answer

If you are applying to the apprenticeship, your test is math, reading and mechanical reasoning, and the IUOE aptitude test page is the one you want. If you are a member working toward a crane card, the test is the OECP written: 75 questions, two hours, no calculator. Start with the questions on this page.

Exam facts checked November 2026 against the OECP Crane Operator Candidate Manual and the OECP FAQ.

Which test are you studying for?

15 operating engineers practice questions

Pick an answer to see if you are right and why. These are original practice questions from the Crane Exam Prep question bank. They are not actual exam questions from OECP or any IUOE local.

  1. Site Setup

    1. Setting up beside a below-grade wall or excavation, supports should stay outside the soil's…

    Show answer

    Answer: A. Angle of repose (zone of influence). Keep supports outside the angle of repose / zone of influence so the crane's surcharge load does not collapse the excavation wall.

  2. Operations

    2. A crane suffers a power failure with a load suspended. What is the preferred response?

    Show answer

    Answer: A. Set the brakes and locking devices, and if practical land the load under brake control rather than leave it hanging. A hanging load with no power is an uncontrolled hazard. Brake-controlled lowering removes the exposure instead of relying on brakes holding indefinitely.

  3. Power Lines

    3. A power line that is "deenergized and grounded" is one that:

    Show answer

    Answer: C. Has been disconnected from its energy source and connected to earth, with the deenergized condition confirmed by the utility owner/operator. Deenergizing and (visibly) grounding, confirmed by the utility, is the only way a line is treated as not energized under OSHA. Visual appearance, low voltage, or weatherproof covering never make a line safe to contact.

  4. Operation Aids

    4. Which operational aid measures the weight of the load itself?

    Show answer

    Answer: C. A load weighing device. A load weighing device reads the load's weight; the LMI combines that weight with radius/angle to compute the load moment.

  5. General Knowledge

    5. What should be of major concern when considering the supporting surfaces for crane setup locations?

    Show answer

    Answer: B. voids, tanks, loose fill, depressions. Voids, buried tanks, loose fill, and depressions can give way under crane loading, so they are the major supporting-surface concern.

  6. Mobile Crane Essentials

    6. What can dynamic (sudden) stopping cause?

    Show answer

    Answer: A. Structural failure. Dynamic stopping shock-loads the crane and can cause structural failure.

  7. Site Setup

    7. When making a lift on outriggers, the maximum ground bearing pressure occurs when the load is over:

    Show answer

    Answer: C. the corner. Maximum ground bearing pressure occurs when the load swings over a corner, because most of the machine and load weight concentrates on that single outrigger float.

  8. Rigging

    8. After rigging is attached, what should be done before making the full lift?

    Show answer

    Answer: B. Lift the load a few inches and check the rigging. Rigging safety rules: lift the load a few inches and check the rigging before proceeding — along with starting and stopping slowly, keeping personnel clear, and maintaining load control. Personnel must never ride the load.

  9. Inspections

    9. Under 1926.1412, the monthly inspection covers the same items as the…

    Show answer

    Answer: D. Each-shift inspection. The monthly inspection covers the same items as the each-shift inspection, but it must be documented; the annual inspection is broader and deeper.

  10. Site Setup

    10. The area that must always be barricaded around a crawler crane is the:

    Show answer

    Answer: C. rear swing radius of the rotating superstructure. OSHA 1926.1424 requires barricading the rotating rear swing radius to protect workers from the counterweight.

  11. Operations

    11. Which platform occupant may extend body parts outside the personnel platform?

    Show answer

    Answer: A. Someone acting as a signal person. All occupants must keep all body parts inside the platform except a person acting as a signal person.

  12. Power Lines

    12. When working near an energized power line, a tag line used to control the load should be:

    Show answer

    Answer: D. Made of a non-conductive material such as synthetic rope. A non-conductive tag line reduces the shock hazard if the load or line contacts electricity.

  13. Operation Aids

    13. A crane manufactured before the anti two-block requirement cutoff dates is…

    Show answer

    Answer: C. Not retroactively required to have an anti two-block device. The anti-two-block requirements apply by manufacture date; older equipment is not retroactively required to have the device, though operators must still guard against two-blocking.

  14. Site Setup

    14. A crane is operating with a long boom, on outriggers, on uneven ground. Under these conditions, it is important to:

    Show answer

    Answer: D. Block under the float or pad to achieve a 90-degree angle between the cylinder rod and the float or pad. On uneven ground you block under the float or pad so the cylinder rod meets the float at 90 degrees — a square, vertical load path prevents side-loading and bending the outrigger jack.

  15. Load Charts

    15. Before using a load chart, the operator must first confirm that:

    Show answer

    Answer: B. The chart matches the specific crane model and its current configuration. A chart applies only to the exact machine and configuration it was issued for.

The OECP written exams at a glance

OECP crane written exams
Questions75 multiple choice for mobile, tower and overhead cranes
Time limit2 hours
Passing scoreScaled score of 500 on a 200 to 800 scale
CalculatorsNot allowed
Who can sit itIUOE members in good standing with 1,000 documented crane hours in the past five years
Signal Person Rigger110 questions in 2 hours

Sources: OECP Crane Operator Candidate Manual and OECP Signal Person Rigger Candidate Manual.

The OECP study guide shows what each exam weights.

FAQ

Operating engineers test questions

Is there one operating engineers test?
No. There is an entrance test to get into a local's apprenticeship, and there are certification exams for members who run cranes or work as signal persons and riggers. They test different things.
What is on the IUOE apprenticeship test?
Usually math, reading and mechanical reasoning, with the details set by each local. What five locals say about their tests.
What is on the OECP crane written exam?
For mobile cranes, the candidate manual lists standards, operations and load charts. It is 75 questions in two hours. Each exam by domain.
Are these real IUOE or OECP test questions?
No. OECP does not release its questions, and locals do not publish their entrance tests. These are original practice questions written from the OSHA crane rules and ASME B30 standards. This site is not affiliated with OECP or the IUOE.
Where can I find more practice questions?
This site has free practice tests for the mobile crane, tower crane and overhead crane exams, and the Crane Exam Prep app has the full question bank.

Keep going

One free practice test shows you where you stand.

25 questions. No sign-up. Every answer explained.

Start the free practice test
More practice questionsFree account, no card
Open the app