The short answer
A rigger test covers sling types and hitches, rigging hardware, inspection and removal criteria, load weight and sling tension. OSHA requires riggers to be qualified for certain work. It does not require them to be certified. For IUOE members, OECP tests rigging and signaling together: 110 questions, and 60% of them are rigging.
Checked November 2026 against the OSHA fact sheet: Qualified Rigger and the OECP Signal Person Rigger Candidate Manual (2025 edition).
Pick an answer to see if you are right and why. These are original practice questions from the Crane Exam Prep question bank, not actual exam questions.
Answer: D. Only on the sling body, never on a weld, braze, or end fitting. The choke point of a metal mesh sling must be on the mesh body, not on a weld, braze, or end fitting.
Answer: D. One half the length of the eye. A wire rope sling eye should not go over a fitting wider than half the eye length, or the eye is forced open and the splice is loaded across its weak axis. Nor should the eye go over a fitting smaller in diameter than the rope itself.
Answer: A. at 90 degrees to the plane of the sling body. A twisted eye sling is an eye-and-eye with twisted terminations so the eye openings sit at 90 degrees to the plane of the sling body.
Answer: C. As the angle between a sling leg and the horizontal decreases, the tension in the sling leg increases. Lower sling angles increase leg tension for the same load, raising the risk of sling overload.
Answer: A. Remove it and add shims (washers) of the proper thickness under the shoulder to rotate the eye into alignment. Machinery eye bolts must be fully seated; to align the eye plane you remove the bolt and add shims of the thickness needed to change the rotation, never leave it partially unscrewed.
Answer: D. 40 times. Braided slings require a minimum clear length of 40 rope diameters, versus 10 diameters for cable laid, 6x19, and 6x37 slings.
Answer: B. The average load at which the product fails or no longer supports the load. Ultimate strength is the average load or force at which the product fails or stops supporting the load. The working load limit is far below it, separated by the design factor.
Answer: D. Wear, deformation, cracks, twisting, and signs of throat opening up. Hook inspection covers wear and deformation at the eye, cracks and twisting in the body, signs of the throat opening up, and wear and cracks in the bowl/saddle.
Answer: D. expose the core yarns. Removal criteria include holes, tears, cuts, abrasive wear or snags that expose the core yarns, weld splatter that exposes core yarns, knotted roundslings, and acid or caustic burns.
Answer: A. Removed from service. Inability to lock is a hook removal criterion — any self-locking hook that does not lock comes out of service.
Answer: C. Away from direct sunlight, heat, moisture, and chemicals. Ultraviolet light, heat, moisture, and chemical fumes degrade synthetic fibers, so slings are stored in a cool, dry, shaded area away from chemicals.
Answer: D. 5,000 lb. Sling tension = (sling length / sling height) x share of load weight = (10 / 8) x 4,000 = 5,000 lb.
Answer: D. 1,280 lb. The plate is 32 sq ft, and 1-inch steel plate weighs 40 lb per sq ft, so 32 x 40 = 1,280 lb.
Answer: B. 6 ft. Distance from the light section = (heavy weight / total) x span = (15,000/20,000) x 8 = 6 ft, so the combined CG is 6 ft from the 5,000 lb section (2 ft from the heavy one).
Answer: A. At least 6,930 lb. Leg tension = 6,000 lb x 1.155 = 6,930 lb, so each sling must be rated for at least 6,930 lb.
Your result
OSHA's construction crane rule calls for a qualified rigger in two situations:
A qualified rigger is a rigger who meets OSHA's test for a qualified person. That is someone with a recognized degree, certificate or professional standing, or with extensive knowledge, training and experience, who can show they can solve problems related to rigging loads.
Three points in OSHA's fact sheet surprise people:
A certification card is still a simple way to show an employer what you know.
25 questions, no sign-up, every answer explained.
OECP does not offer a rigger-only card. Rigging and signaling are one certification with one written exam: 110 multiple-choice questions in two hours, with 500 as the passing score on a scale of 200 to 800.
| Domain | Share | What it covers |
|---|---|---|
| A. Rigging standards | 20% | Rigging near energized power lines, slings and rigging hardware, personnel platform rigging, inspections and removal from service |
| B. Rigging operations | 30% | Sling hitches and hoisting hardware, blocking and cribbing, wire rope, synthetic and chain slings, tag lines and knots, center of gravity, storage and care. Also pre-lift planning, lockout and tagout, overloads, boom deflection, the fall zone and ground stability |
| C. Rigging calculations | 10% | Working out load weights and sling tension |
| D. Signaling | 40% | Hand, voice and radio signals, basic crane components and limits, and job site safety. More on the signaling side |
Source: OECP Signal Person Rigger Candidate Manual, written examination outline.
Personal calculators are not allowed, so the calculations domain is pencil work. Practice load weight and sling tension by hand.
The Signal Person Rigger practical has four tests worth 350 points in all, and 261 passes. Two of the four are rigging.
| Test | What you do |
|---|---|
| Rigging inspection | Untimed. You get five minutes to look over undamaged components first. Then you identify each item and state its inspection points |
| Rigging practical | Untimed, in three parts: a choke hitch, a double wrap basket hitch and a vertical hitch with a shackle. Points come off for the wrong sling or hardware, an improper hitch, a tag in the wrong place and twists |
Source: OECP Signal Person Rigger Candidate Manual, practical examination section.
An unsafe action that endangers people fails the practical on the spot.
| Sling tension | Share of the load x sling length divided by vertical height |
|---|---|
| Load angle factors | 1.155 at 60 degrees from horizontal, 1.414 at 45 degrees, 2.0 at 30 degrees |
| Steel plate | About 40 lb per square foot for each inch of thickness |
| Fresh water | 62.4 lb per cubic foot |
| Combined center of gravity | Distance from the lighter piece = heavier weight divided by total weight x the distance between the two centers |
FAQ
Guide
What OSHA requires, the OECP exam and 12 practice questions.
Signal person certificationPractice test
One OECP certification for signaling and rigging together.
Signal person rigger practice testPractice test
Load weight, sling tension and parts of line, worked by hand.
Load calculations practice test25 questions. No sign-up. Every answer explained.