Guide
Load moment indicator (LMI)
What an LMI does, when OSHA requires one, and the other operational aids.
Load moment indicator (LMI)Load charts
A load chart answers one question: what may this crane lift, set up this way, at this radius? Reading one is a fixed routine. On the OECP written you do it with a pencil, because calculators are not allowed.
The short answer
Reading a load chart takes five steps: match the chart to the crane's configuration, find the boom length, find the radius, read the gross capacity, then subtract the deductions such as the hook block and rigging to get net capacity. When your radius or boom length falls between two listed values, follow the chart's note, which usually sends you to the lower capacity.
Checked November 2026 against the text of 29 CFR 1926.1417, 29 CFR 1926.1433 and the OECP Crane Operator Candidate Manual.
Then check parts of line. The hoist line has its own limit, and the chart tells you how many parts you need for the load.
Pick an answer to see whether you are right and why. These are original practice questions from the Crane Exam Prep question bank, not actual exam questions.
Answer: D. The weight of the hook block, rigging, and other applicable deductions. Deductions such as the hook block, downhaul weight, slings, and attachments must be subtracted from gross chart capacity to find the net capacity for the load itself.
Answer: D. Short boom set at its highest working angle. Rated tonnage is a chart maximum, not an all-conditions number. The same 60 ton crane on a long boom at a low angle may only rate a few thousand pounds.
Answer: A. Level, on a firm supporting surface. Rated capacities are only valid with the crane level on firm support — anything less reduces real capacity.
Answer: D. The 90-foot column — the next longer boom length. This chart's note sends you to the next longer listed length, 90 ft. Other manufacturers instead say to use whichever adjacent length gives the smaller rating — always follow the note on the chart you are using.
Answer: C. The number of rope lines supporting the load block, which multiplies the lifting capability of a single line pull. Parts of line is how many rope falls support the block. Ignoring friction, the load that can be lifted equals the permissible single-line pull times the number of parts of line.
Answer: C. stability (the crane tips first). Below the bold line ratings are stability-limited; above the line they are limited by structural strength.
Answer: D. Boom angle. Length, radius, and angle are geometrically linked; charts work from any two.
Answer: C. As part of the load (added into the net load / deducted from capacity). The chart notes state that weights of slings and all other load-handling devices are considered part of the load, so they must be added to the load being lifted.
Your result
25 questions, no sign-up, every answer explained.
| Term | Meaning |
|---|---|
| Gross capacity | The number printed on the chart for a boom length and radius |
| Deductions | The weight of the hook block, ball, rigging and attachments that the chart says to subtract |
| Net capacity | Gross capacity minus deductions. The most the load itself may weigh |
| Radius | Horizontal distance from the center of rotation to the center of the loaded hoist line |
| Parts of line | The number of rope lines supporting the load block |
| Bold line or shading | Many charts mark the boundary between ratings limited by structural strength and ratings limited by stability |
| Range diagram | The drawing that shows boom tip height against radius for each boom length and angle |
| Work area | The zones over the front, side and rear in which a rating applies |
| In the cab | The rated capacities, load charts and related information must be available in the cab |
|---|---|
| Rated capacity | The equipment must not be operated beyond it |
| Load weight | Known before the lift from a reliable source, a calculation or a load weighing device |
| The 75% check | If a load weighing device or LMI shows the load is over 75% of rated capacity at the longest radius to be used, the operator does not proceed until the weight is verified |
| Hook block | Hook and ball assemblies and load blocks must be marked with their rated capacity and weight |
| Wind, ice and snow | A competent person adjusts the equipment or the operation for their effect on stability and rated capacity |
Sources: 29 CFR 1926.1417 and 29 CFR 1926.1433.
OECP's candidate manual includes sample load charts so you know what to expect: a Manitowoc 222 for mobile cranes and a Peiner SK 405 for tower cranes. It also says personal calculators are not allowed, so the subtraction is done by hand.
Get quick at the arithmetic before exam day. Take the free load calculation practice test, then work through the OECP study guide.
FAQ
Guide
What an LMI does, when OSHA requires one, and the other operational aids.
Load moment indicator (LMI)Guide
Each written exam by domain, the references OECP names and a study plan.
OECP study guidePractice test
Load weight, sling tension and parts of line, worked by hand.
Load calculations practice test25 questions. No sign-up. Every answer explained.