Crane operator requirements
What OSHA requires: training, certification or a license, and evaluation.
Crane operator requirementsOSHA crane standard
Subpart CC is OSHA's standard for cranes and derricks in construction. It runs from 1926.1400 to 1926.1442, and it is on the reference list for every OECP crane exam. This page maps the sections and the numbers that get tested.
The short answer
29 CFR 1926 Subpart CC covers power-operated construction equipment that can hoist, lower and horizontally move a suspended load. Its core rules: the 20-foot power line trigger and Table A clearances, shift, monthly and annual inspections, a qualified signal person and qualified rigger where required, and operators who are trained, certified or licensed, and evaluated.
Checked November 2026 against the text of OSHA 29 CFR 1926 Subpart CC in the Code of Federal Regulations.
Section numbers are worth learning. Exam questions and jobsite paperwork both cite them.
| Section | Covers | Number to know |
|---|---|---|
| 1926.1400 | Scope | Equipment that hoists, lowers and horizontally moves a suspended load |
| 1926.1402 | Ground conditions. More | Ground must be firm, drained and graded |
| 1926.1404 | Assembly and disassembly. More | Directed by a competent and qualified person |
| 1926.1408 | Power line safety. More | 20-foot trigger. 10 feet up to 50 kV |
| 1926.1412 | Inspections. More | Each shift, monthly, every 12 months |
| 1926.1413 | Wire rope inspection. More | Six broken wires in one rope lay |
| 1926.1416 | Operational aids. More | Repair within 7 or 30 calendar days |
| 1926.1417 | Operation | Two full wraps left on the drum |
| 1926.1419 | Signals. More | One signal person at a time |
| 1926.1425 | Keeping clear of the load | Qualified rigger in the fall zone |
| 1926.1427 | Operator certification. More | Certification valid five years |
| 1926.1428 | Signal person qualifications. More | Oral or written test plus a practical |
| 1926.1431 | Hoisting personnel. More | 50% of rated capacity |
| 1926.1432 | Multiple-crane lifts. More | A plan and a lift director |
| 1926.1435 | Tower cranes. More | Plumb to 1:500 |
| 1926.1438 | Overhead and gantry cranes. More | Permanent installs follow 1910.179 |
Source: OSHA 29 CFR 1926 Subpart CC.
Pick an answer to see whether you are right and why. These are original practice questions from the Crane Exam Prep question bank, not actual exam questions.
Answer: B. Safely stop operations; the equipment must be taken out of service and operations must not resume until the device is working properly. 1926.1415(b) requires stopping operations and taking the equipment out of service until the device works properly; alternative measures are NOT permitted for safety devices, unlike operational aids.
Answer: D. A qualified person, with disassembly as necessary to complete the inspection. 1926.1412(f)(2) requires a qualified person to inspect at least every 12 months, with disassembly as necessary.
Answer: C. 75 percent. 1926.1417(o)(3)(ii) requires the operator to determine, using a load weighing/moment device, whether the load exceeds 75 percent of maximum rated capacity at the longest radius; if it does, the weight must be verified before proceeding.
Answer: D. Two full wraps. 1926.1417(t) requires at least two full wraps of rope to remain on the drums.
Answer: D. The assembly or disassembly of equipment such as booms, jibs, and crane components, covered by 1926.1403-1406. A/D refers to erecting or dismantling crane components (boom sections, jibs, counterweights) and is governed by dedicated Subpart CC provisions.
Answer: C. 1:500 (approximately 1 inch in 40 feet). 1926.1435(b)(5) requires plumb to at least 1:500 (about 1 inch in 40 feet) verified by a qualified person when the manufacturer does not specify a tolerance.
Answer: C. Rubber-tired equipment. 1926.1431(k)(12)(i)(C) states the travel exception does not apply to rubber-tired equipment; where allowed, travel must be restricted to a fixed track or runway, limited to boom length, with the boom parallel to travel and a trial run performed.
Answer: B. Boom hoist limiting device. 1926.1416(d) Category I includes the boom hoist limiting device, luffing jib limiting device, and anti two-blocking device. Indicators like boom angle/radius are Category II under (e).
Your result
25 questions, no sign-up, every answer explained.
| Rated capacity | The equipment must never be operated beyond its rated capacity |
|---|---|
| Load weight | Verified from a reliable source, by calculation or with a load weighing device. If a check with a load weighing device or load moment indicator shows more than 75% of rated capacity at the longest radius, the operator does not proceed until the weight is verified |
| Brake test | When the load is 90% or more of the maximum line pull, lift it a few inches and apply the brakes |
| Rope on the drum | Never fewer than two full wraps when lowering the load or the boom |
| Stop signals | The operator obeys a stop or emergency stop signal no matter who gives it |
| Authority to stop | The operator can stop and refuse to handle a load when there is a safety concern, until a qualified person determines it is safe |
| Travel with a load | Only where the manufacturer allows it, with a competent person supervising |
Sources: 29 CFR 1926.1417 and 29 CFR 1926.1418.
Much of the rule turns on who is allowed to make a decision. The definitions are in 1926.1401.
| Role | Definition, in short |
|---|---|
| Competent person | Can identify existing and predictable hazards, and has the authority to take prompt corrective measures |
| Qualified person | Has a recognized degree, certificate or professional standing, or extensive knowledge, training and experience, and has shown the ability to solve problems in the subject |
| Qualified rigger | A rigger who meets the criteria for a qualified person |
| A/D director | The person who meets the rule's requirements for directing assembly and disassembly, whatever the job title |
| Controlling entity | The prime or general contractor, or another entity with overall responsibility for the project |
| Dedicated spotter | Meets the signal person qualifications, and whose only job is watching the clearance between the equipment and a power line |
Source: 29 CFR 1926.1401.
Section 1926.1400 lists exclusions. Among them:
Three kinds of equipment are inside the rule but outside operator certification: derricks, sideboom cranes and equipment rated at 2,000 pounds or less. Their operators must still be trained.
FAQ
Guide
What OSHA requires: training, certification or a license, and evaluation.
Crane operator requirementsGuide
OSHA Table A distances, the 20-foot rule and what to do before you set up.
Crane power line clearanceGuide
OSHA's shift, monthly and annual inspections, item by item.
Crane inspection checklist25 questions. No sign-up. Every answer explained.