Guide
Lift director
What a lift director does under ASME B30.5 and OSHA, with questions.
Lift directorASME crane standard
B30.5 is the ASME safety standard for mobile cranes. OSHA's construction crane rule borrows from it, and OECP lists it among the references for the mobile crane written exam.
The short answer
ASME B30.5 applies to crawler, locomotive and wheel-mounted cranes. It covers construction and characteristics, inspection, testing, maintenance and operation. It also assigns jobsite responsibilities to the crane owner, crane user, site supervisor, lift director and crane operator. The current edition is B30.5-2025.
Checked November 2026 against the Mazzella reference guide to the ASME B30 standards, the ASME B30.5-2025 title pages and an NCCCO article on jobsite responsibilities under ASME B30.5.
| Title | Mobile and Locomotive Cranes |
|---|---|
| Applies to | Crawler cranes, locomotive cranes and wheel-mounted cranes, powered by engines or electric motors |
| Does not apply to | Side boom tractors, cranes built for wreck clearance, digger derricks, cranes built for energized power line work, knuckle boom and trolley boom cranes, and cranes rated at one ton or less |
| Current edition | B30.5-2025, a revision of B30.5-2021 |
| Part of | The ASME B30 safety standard for cableways, cranes, derricks, hoists, hooks, jacks and slings |
Sources: Mazzella reference guide to the ASME B30 standards and ASME B30.5-2025 title pages.
ASME sells its standards and does not publish the text for free. This page describes what the volume covers and how it is organized, from published summaries. The practice questions cite the paragraphs they are drawn from. For clause-level work, use a current copy of the standard.
Pick an answer to see whether you are right and why. These are original practice questions from the Crane Exam Prep question bank, not actual exam questions.
Answer: A. While the engine is running. Para 5-3.4.9(b) prohibits refueling while the engine is running; gasoline refueling from portable containers requires a safety-type can with automatic closing cap and flame arrester.
Answer: B. 4 ft (1.2 m). Table 5-3.4.5.1-1 transit clearances are 4 ft up to 0.75 kV, 6 ft over 0.75 to 50 kV, 10 ft over 50 to 345 kV, and 16 ft over 345 to 750 kV.
Answer: A. 5%. Para 5-2.4.3(b)(6) requires removal when reduction from nominal diameter exceeds 5%.
Answer: D. In a location accessible to the operator while at the controls. Para 5-1.1.3(b) requires the chart to be provided with each crane and attached in a location accessible to the operator while at the controls.
Answer: A. 1-month to 12-month intervals. Para 5-2.1.1(b)(2) defines periodic inspection intervals as 1 month to 12 months, depending on activity, severity of service, and environment.
Answer: B. Two randomly distributed broken wires in six rope diameters or four in 30 rope diameters. Para 5-2.4.3(b)(1)(-b) sets removal at two broken wires in six rope diameters or four broken wires in 30 rope diameters for rotation-resistant ropes.
Answer: A. In line with the direction of motion. Para 5-3.2.1.5(n) states the boom should be carried in line with the direction of motion, with the superstructure secured against rotation and the empty hook lashed.
Answer: C. Determined after consultation with the utility owner/operator. Table 5-3.4.5.1-1 requires the specified clearance over 1,000 kV to be determined after consultation with the utility owner or operator.
Your result
25 questions, no sign-up, every answer explained.
| Chapter | Subject | What you find there |
|---|---|---|
| 5-0 | Scope, definitions, personnel competence and references | Crane types and the vocabulary the rest of the standard uses |
| 5-1 | Construction and characteristics | Load ratings and stability, boom hoists, brakes, ropes and sheaves, controls and cabs |
| 5-2 | Inspection, testing and maintenance | Frequent and periodic inspections, rope inspection and removal, load testing |
| 5-3 | Operation | Operator qualifications, responsibilities, handling the load, signals, power lines |
Source: Mazzella reference guide to the ASME B30 standards, with paragraph examples from the practice questions on this page.
B30.5 assigns responsibilities to named roles, and some of them overlap on purpose so that nothing important is missed. The summary below follows NCCCO's published explanation.
| Role | Responsible for |
|---|---|
| Crane owner | Providing a crane that meets the standard, its technical information, and an inspection, testing and maintenance program |
| Crane user | Using qualified supervisors and operators, confirming the crane has the capacity for the work and that inspections are done |
| Site supervisor | Making sure the crane is inspected, the crane area is prepared, operators meet the requirements, and a qualified person is designated lift director |
| Lift director | Directly overseeing the lift and the rigging crew, and carrying out the lift plan |
| Crane operator | Operating the crane. Operators must meet the standard's qualification requirements |
Source: NCCCO article on jobsite responsibilities under ASME B30.5.
On a small job one person can hold more than one role. The 2018 edition added responsibilities for the rigger.
B30.5 is a consensus standard, not a regulation. OSHA's construction crane rule pulls parts of it into law. For example, 1926.1433 requires mobile cranes built on or after November 8, 2010 to meet listed portions of ASME B30.5-2004.
Where the two overlap, they usually agree on the numbers. Both use 5% loss of nominal diameter as a wire rope removal point. OSHA Subpart CC, section by section.
FAQ
Guide
What a lift director does under ASME B30.5 and OSHA, with questions.
Lift directorGuide
The construction crane rule, section by section, with the numbers to know.
OSHA 1926 Subpart CCPractice test
One written exam for boom truck, lattice boom and telescopic boom.
Mobile crane practice test25 questions. No sign-up. Every answer explained.