The overhead and gantry crane rule: clearances, brakes, inspections and loads.
OSHA 1910.179ASME overhead crane standard
B30.2 is the ASME standard for the overhead cranes found in shops, mills and plants. OSHA's overhead crane rule was written around its 1967 edition, and OECP lists the standard among its exam references.
The short answer
ASME B30.2 applies to overhead and gantry cranes with a top-running bridge and a top-running trolley hoist, hand operated or power driven, used for vertical lifts of unguided loads. It covers construction and installation, inspection and testing, operation and maintenance. Underhung cranes are covered by B30.17, not B30.2.
Checked November 2026 against the Mazzella reference guide to the ASME B30 standards, 29 CFR 1910.179 and 29 CFR 1926.1438.
| Title | Overhead and Gantry Cranes (Top Running Bridge, Single or Multiple Girder, Top Running Trolley Hoist) |
|---|---|
| Applies to | Hand-operated and power-driven overhead and gantry cranes with a top-running single-girder or multiple-girder bridge and one or more top-running trolley hoists |
| Also included | Cranes of the same basic kind, such as cantilever gantry, semi-gantry and wall cranes |
| Used for | Vertical lifting and lowering of freely suspended, unguided loads |
| Not covered | Special-purpose cranes, such as those for non-vertical lifts, guided loads or lifting people |
| Underhung cranes and monorails | Covered by ASME B30.17 |
ASME sells its standards and does not publish the text for free. This page describes what the volume covers and how it is organized, from published summaries. The practice questions cite the paragraphs they are drawn from. For clause-level work, use a current copy of the standard.
Pick an answer to see whether you are right and why. These are original practice questions from the Crane Exam Prep question bank, not actual exam questions.
Answer: C. Twelve randomly distributed broken wires in one lay or four broken wires in one strand in one lay. Removal criteria include twelve randomly distributed broken wires in one lay or four broken wires in one strand in one lay.
Answer: D. Operation of the upper limit device under no-load conditions, inching the block into the limit or running in at slow speed. Prior to initial use during each shift, the operator shall verify operation of the upper limit device under no-load conditions, with care exercised by inching the block into the limit or running in at slow speed; if it does not operate properly, the operator shall immediately notify the designated person.
Answer: D. 10 BC. A portable fire extinguisher with a basic minimum extinguisher rating of 10 BC shall be installed in the cab.
Answer: A. A crane not in regular service that is used occasionally or intermittently as required. A standby crane is a crane not in regular service that is used occasionally or intermittently as required.
Answer: B. Shall not exceed the upper limit of travel, whether loaded or empty. Power-driven hoists shall be designed so the load block, either loaded or empty, shall not exceed the upper limit of travel.
Answer: D. The rails must be secured to withstand the resultant forces applied by the clamp, and the clamping area kept free of projections or obstructions. A clamp is only as good as what it grips. If the rail can lift or shift, or the jaws land on an obstruction, the clamp will not hold, and clamps are applied only when the crane is not in motion.
Answer: C. With the U-bolt over the dead end of the rope and the live rope resting in the clip saddle. U-bolt clips shall have the U-bolt over the dead end of the rope and the live rope resting in the clip saddle; clips shall be tightened evenly and nuts retightened after initial loading.
Answer: D. Verify the weight of the total load before lifting. The operator shall verify the weight of the total load if there is a question whether it exceeds the rated load of the crane and/or hoist(s), and shall not use a load-limiting device to measure the load.
Your result
25 questions, no sign-up, every answer explained.
| Chapter | Subject |
|---|---|
| 2-0 | Scope, definitions, references and personnel competence |
| 2-1 | General construction and installation |
| 2-2 | Inspection and testing |
| 2-3 | Operator training and operation |
| 2-4 | Maintenance training and maintenance |
OSHA's rule for these cranes is 29 CFR 1910.179. It requires overhead and gantry cranes installed on or after August 31, 1971 to meet the design specifications of ANSI B30.2.0-1967, the standard's edition at the time.
On construction sites, 29 CFR 1926.1438 points to a later edition. An overhead or gantry crane that is not permanently installed in a facility must meet parts of ASME B30.2-2005 if it was built on or after September 19, 2001.
The standard has been revised many times since 1967, and it now goes further than the regulation in places. One example from the questions above: B30.2 gives a numeric broken-wire count for running ropes, while 1910.179 requires a monthly rope inspection without one. OSHA 1910.179 in detail.
FAQ
Guide
The overhead and gantry crane rule: clearances, brakes, inspections and loads.
OSHA 1910.179Guide
Frequent and periodic inspections under OSHA 1910.179, with questions.
Overhead crane inspectionPractice test
Its own written exam for overhead crane operators.
Overhead crane practice test25 questions. No sign-up. Every answer explained.