Overhead crane inspectionOSHA overhead crane standard
1910.179 is OSHA's general industry rule for overhead and gantry cranes. It is on OECP's reference list for the crane exams, and it is full of specific numbers. The ones worth knowing are below.
The short answer
29 CFR 1910.179 applies to overhead and gantry cranes, including semigantry, cantilever gantry, wall and storage bridge cranes. It requires the rated load marked on each side of the crane, 3 inches of overhead and 2 inches of lateral clearance, frequent and periodic inspections, a monthly rope inspection with a signed record, and at least two wraps of rope on the drum.
Checked November 2026 against the text of 29 CFR 1910.179 in the Code of Federal Regulations (OSHA's page for the section) and 29 CFR 1926.1438.
| Who may operate | Only designated personnel, under (b)(8) |
|---|---|
| Design standard | Cranes installed on or after August 31, 1971 must meet ANSI B30.2.0-1967, under (b)(2) |
| Rated load marking | On each side of the crane, and on each hoist or load block when there is more than one hoisting unit, under (b)(5) |
| Clearance from obstructions | At least 3 inches overhead and 2 inches laterally, under (b)(6) |
| Footwalk headroom | At least 48 inches, under (d)(1) |
| Holding brake torque | At least 125% of full load hoisting torque with non-mechanical control braking, or 100% with mechanical control braking, under (f)(2) |
| Pendant push-button voltage | No more than 150 volts AC or 300 volts DC, under (g)(1) |
| Pendant buttons | Return to the off position when released, under (g)(3) |
| Rope loading | Rated load divided by the number of parts of rope must not exceed 20% of the rope's nominal breaking strength, under (h)(2) |
| Rope on the drum | At least two wraps with the hook in its lowest position, under (h)(2) |
| Rope clips | The U-bolt goes on the dead, or short, end of the rope, under (h)(2) |
| Warning device | A gong or other warning signal on power-traveling cranes, except floor-operated ones, under (i) |
| Rated load test | Not more than 125% of the rated load, unless the manufacturer recommends otherwise, under (k)(2) |
Source: 29 CFR 1910.179. Read the section on OSHA's site.
Pick an answer to see whether you are right and why. These are original practice questions from the Crane Exam Prep question bank, not actual exam questions.
Answer: B. The switch or circuit breaker. OSHA requires the runway conductors' power supply to be controlled by a switch or circuit breaker so power can be positively disconnected, e.g. for maintenance or emergencies.
Answer: B. Automatic rail clamps and a wind indicator with alarm at a predetermined wind velocity. Outdoor storage bridges must have automatic rail clamps and a wind indicator giving a visible or audible alarm at a predetermined wind velocity.
Answer: C. limit the hoist travel. The upper limit switch limits hoist travel, stopping the block before it contacts the trolley; it is the only limit switch OSHA 1910.179 specifically requires.
Answer: C. Specifically authorized by a responsible person. OSHA 1910.179 prohibits side pulls unless a qualified/responsible person specifically authorizes it after determining the crane won't be damaged and stability isn't endangered.
Answer: C. 20 percent. Hoist rope strength requires that rated load divided by number of parts of rope not exceed 20 percent of the rope's normal breaking strength — a 5:1 factor.
Answer: D. 2 wraps. OSHA 1910.179 requires no less than two wraps of rope to remain on the drum when the hook is in its lowest position, so the rope anchor is never the sole attachment carrying the load.
Answer: C. clearly marked on the side of the crane. OSHA 1910.179 requires the rated load to be plainly marked on each side of the crane so it is legible from the ground or floor.
Your result
25 questions, no sign-up, every answer explained.
The rule sorts inspections by how often they happen.
| Inspection | When | What |
|---|---|---|
| Initial | Before first use of a new or altered crane | The whole crane |
| Frequent | Daily to monthly intervals | Operating mechanisms, air and hydraulic leaks, hooks and hoist chains. Hooks and chains get a monthly inspection with a certification record |
| Periodic | Intervals of 1 to 12 months | Structure, brakes, power plant and electrical items |
| Running ropes | At least once a month | A thorough inspection with a signed certification record |
| Idle one month to under six months | Before going back into service | A frequent-type inspection plus the rope inspection |
| Idle more than six months | Before going back into service | A complete inspection |
| Standby cranes | At least every six months | A frequent-type inspection plus the rope inspection |
Source: 29 CFR 1910.179(j) and (m).
Overhead crane inspection in more detail, with practice questions.
Paragraph (n) sets the basic handling rules:
Paragraph (l) covers maintenance. Before repairs start, the crane is run to a spot where it interferes least, all controllers are set to off, the main switch is opened and locked, and warning or out of order signs go up. Rail stops protect it if other cranes share the runway. The employer must also keep a preventive maintenance program based on the manufacturer's recommendations.
OSHA's construction crane rule hands some overhead cranes back to 1910.179. Under 29 CFR 1926.1438, an overhead or gantry crane that is permanently installed in a facility follows 1910.179 and not Subpart CC.
One that is not permanently installed follows Subpart CC, along with parts of 1910.179 and ASME B30.2-2005 for cranes built on or after September 19, 2001. More on ASME B30.2.
FAQ
Guide
Frequent and periodic inspections under OSHA 1910.179, with questions.
Overhead crane inspectionGuide
The overhead and gantry crane standard: scope, chapters and questions.
ASME B30.2Guide
Requirements, the written domains, the practical and practice questions.
OECP overhead crane certification25 questions. No sign-up. Every answer explained.