Guide
OSHA 1910.179
The overhead and gantry crane rule: clearances, brakes, inspections and loads.
OSHA 1910.179Inspections
Overhead and gantry cranes in a facility are inspected under OSHA 1910.179, not the construction crane rule. It sorts inspections into frequent and periodic, and asks for signed records on a few specific items.
The short answer
OSHA 1910.179 requires an initial inspection before a new or altered overhead crane is used, frequent inspections at daily to monthly intervals, and periodic inspections at intervals of 1 to 12 months. Hooks, hoist chains and running ropes each need a monthly inspection with a signed certification record.
Checked November 2026 against the text of 29 CFR 1910.179 (OSHA's page for the section) and the Mazzella reference guide to the ASME B30 standards.
| Inspection | Interval | Covers |
|---|---|---|
| Initial | Before first use of a new or altered crane | The crane as a whole |
| Frequent | Daily to monthly | Items checked every day, and items checked monthly with a record |
| Periodic | 1 to 12 months | A complete inspection, including the frequent items plus structure, brakes, power plant and electrical equipment |
Source: 29 CFR 1910.179(j).
How often inside those ranges depends on how hard the crane works: its activity, the severity of service and its environment.
| Item | How often | Record |
|---|---|---|
| Functional operating mechanisms, for maladjustment | Daily | Not required |
| Air and hydraulic system lines, tanks, valves and pumps, for deterioration or leaks | Daily | Not required |
| Hooks, for deformation or cracks | A visual check daily, and an inspection monthly | A certification record for the monthly inspection |
| Hoist chains and end connections | A visual check daily, and an inspection monthly | A certification record for the monthly inspection |
| Running ropes | A thorough inspection at least once a month | A signed certification record |
Source: 29 CFR 1910.179(j)(2) and (m)(1).
25 questions, no sign-up, every answer explained.
Pick an answer to see whether you are right and why. These are original practice questions from the Crane Exam Prep question bank, not actual exam questions.
Answer: B. Sections in contact with saddles and equalizer sheaves, sections at or near terminal ends, sections subject to reverse bends, and sections normally hidden. Special care applies to sections in contact with saddles or equalizer sheaves where travel is limited, sections at or near terminal ends where broken wires may protrude, sections subject to reverse bends, and sections normally hidden such as parts passing over sheaves.
Answer: B. Each motion shall be inched or operated at low speed into the limit device with no load on the crane. Motion limit devices shall be checked by inching each motion or operating at low speed into the limit device with no load on the crane.
Answer: B. Daily to weekly. For frequent inspections: normal = monthly, heavy = weekly to monthly, severe = daily to weekly.
Answer: C. Functional operating mechanisms, controls, safety devices, hooks, load-bearing rope and chain, and the brake system. Daily frequent inspection covers operating mechanisms, controls, safety devices, hooks, load-bearing rope/chain, bolts, brake system, and warning/capacity markings; items like drums, sheaves, and electrical apparatus are periodic (semi-annual).
Answer: B. Five: initial, functional test, frequent, periodic, and inspection of equipment not in regular use. Five inspection types are defined: initial, functional test, frequent, periodic, and inspection of equipment not in regular use.
Answer: A. A designated person performs inspections; a qualified person determines whether deficiencies constitute a hazard. All inspections shall be performed by a designated person; any deficiencies shall be examined and a determination made by a qualified person as to whether they constitute a hazard.
Answer: C. The emergency stop functions properly. The pre-operational (daily) inspection covers the crane's own operating functions — including verifying the emergency stop works — before any lifting begins.
Answer: D. It carries the rope section that equalizes rope lengths and sees little movement, so that rope section requires careful inspection. The rope in contact with and adjacent to equalizing sheaves moves very little and is a listed critical inspection point.
Your result
| Idle one month or more, but less than six months | A frequent-type inspection and a rope inspection before it goes back into service |
|---|---|
| Idle more than six months | A complete inspection before it goes back into service |
| Standby cranes | Inspected at least every six months |
| Ropes idle a month or more | A thorough inspection by an appointed person before use |
Source: 29 CFR 1910.179.
| Operational tests | Before first use, new and altered cranes are tested for hoisting and lowering, trolley travel, bridge travel, and limit switches and safety devices |
|---|---|
| Hoist limit switch | The trip setting is found by tests with an empty hook, at increasing speeds up to the maximum |
| Rated load test | Test loads are not more than 125% of the rated load, unless the manufacturer recommends otherwise |
| Reports | Test reports are kept on file |
Source: 29 CFR 1910.179(k).
Most overhead crane inspection programs are built on ASME B30.2 as well as the OSHA rule. Its chapter on inspection and testing is more detailed, and several of the practice questions above are drawn from it. What ASME B30.2 covers.
The lifting gear under the hook has its own inspections. Below-the-hook lifting devices and sling inspection.
FAQ
Guide
The overhead and gantry crane rule: clearances, brakes, inspections and loads.
OSHA 1910.179Guide
The overhead and gantry crane standard: scope, chapters and questions.
ASME B30.2Guide
Requirements, the written domains, the practical and practice questions.
OECP overhead crane certification25 questions. No sign-up. Every answer explained.