Assembly/disassembly director: the A/D director's job

Putting a crane together and taking it apart is where a lot of crane accidents happen. OSHA puts one person in charge of it and spells out what that person has to do.

The short answer

Under 29 CFR 1926.1404, crane assembly and disassembly must be directed by a person who is both a competent person and a qualified person, or by a competent person assisted by qualified persons. OSHA calls this the A/D director, whatever the job title. The A/D director must understand the procedures and review them with the crew before work starts.

Checked November 2026 against the text of 29 CFR 1926.1404, 29 CFR 1926.1401 and 29 CFR 1926.1435.

What the A/D director must do

Duties in 29 CFR 1926.1404
Who qualifiesA person who meets the criteria for both a competent person and a qualified person, or a competent person who is assisted by one or more qualified persons
Know the procedureThe A/D director must understand the assembly and disassembly procedures that apply
Brief the crewBefore work starts, make sure the crew understands their tasks, the hazards of those tasks, and the positions and locations to stay out of
Brief againWhen a task changes or a new person joins the crew
Crew out of viewBefore a crew member goes somewhere the operator cannot see and where equipment movement could injure them, the operator must be told
RiggingRigging work during assembly and disassembly must be done by a qualified rigger
Synthetic slingsProtected from abrasive, sharp or acute edges and used as the sling manufacturer instructs

Source: 29 CFR 1926.1404. Definitions are in 29 CFR 1926.1401.

8 practice questions on assembly and disassembly

Pick an answer to see whether you are right and why. These are original practice questions from the Crane Exam Prep question bank, not actual exam questions.

  1. A/D Director — Core

    1. When an A/D operation must continue after dark, the A/D director must ensure:

    Show answer

    Answer: A. Adequate illumination of the work area, hazards, staging, and signal locations. Monitoring site conditions during execution includes providing adequate lighting so hazards, crew positions, and signals remain visible.

  2. A/D Director — Core

    2. Before pins connecting a boom section are removed during disassembly, the A/D director must ensure the section is:

    Show answer

    Answer: A. Supported, blocked, or secured so it cannot move unintentionally when the pins are pulled. 1926.1404(h)(7) requires that component stability upon pin removal be addressed so components are blocked/secured/supported against unintended dangerous movement.

  3. A/D Director — Core

    3. Which statement about stop-work authority during assembly/disassembly is correct?

    Show answer

    Answer: D. If the A/D director or a crew member identifies an unsafe condition, work must stop until the hazard is corrected. The A/D director must address unsafe conditions; recognized hazards require stopping work until corrected, and crew members can and should raise safety concerns.

  4. A/D Director — Core

    4. Before the boom-hoist system is disconnected during disassembly, the A/D director must confirm:

    Show answer

    Answer: C. The boom-hoist brake is functional (or another means is used) so the boom cannot free-fall. 1926.1404(h)(10): each time the boom hoist brake will be relied on to hold the boom during A/D, it must first be tested to confirm it can prevent boom movement; if it cannot, a boom hoist pawl, other locking/back-up braking device, blocking, or an assist crane must be used so the boom cannot fall.

  5. A/D Director — Core

    5. Why is the boom tip blocked up when boom sections are assembled on the ground?

    Show answer

    Answer: A. To protect the sheave guards from being crushed. Resting the tip directly on the ground can bend or crush the sheave guards and damage the sheaves. Blocking holds the tip clear while sections are pinned.

  6. A/D Director — Core

    6. If a crew member must work in a position out of the operator's view during disassembly, the A/D director must ensure:

    Show answer

    Answer: B. A qualified signal person relays signals, or operations that could endanger the crew member are suspended until they return to view. 1926.1404(e) requires protecting out-of-view crew via signals/notification and suspending endangering operations until they are back in view or have informed the director.

  7. A/D Director — Core

    7. As part of verification after assembly and before the crane is placed in service, the A/D director should confirm that:

    Show answer

    Answer: A. The assembled configuration matches a rated configuration in the manufacturer's load chart. The crane must be assembled to a configuration listed in the manufacturer's load charts so rated capacities apply; verifying this is part of confirming safe assembly.

  8. A/D Director — Core

    8. When setting up a crane for assembly near an open excavation, the A/D director's PRIMARY ground-related concern is to:

    Show answer

    Answer: B. Keep the crane and its outrigger/crawler loads outside the excavation's zone of influence so the ground cannot fail beneath the supports. Setup loads placed within an excavation's angle of repose can cause ground failure; the A/D director must assess site and ground bearing conditions per 1926.1404(h)(1).

Free OECP practice test

25 questions, no sign-up, every answer explained.

Start now

Outriggers and stabilizers during setup

From 1926.1404(q)
ExtensionFully extended, or deployed as the load chart specifies
WheelsOutriggers are set to take the weight of the equipment off the wheels, except on locomotive cranes
FloatsAttached to the outriggers when used
VisibilityEach outrigger or stabilizer is visible to the operator or to a signal person while it is extended or set
BlockingPlaced only under the outrigger or stabilizer float or pad, or under the outer bearing surface of the extended beam

Source: 29 CFR 1926.1404, paragraph (q).

Tower cranes and derricks

For tower cranes OSHA uses the words erecting, climbing and dismantling, and applies the same rules. Under 1926.1435 the A/D director must also address the foundation and structural supports, backward stability and wind speed. Tower crane erecting, climbing and dismantling.

For derricks, 1926.1436 puts the A/D director in charge of jumping the derrick.

Is there an A/D director certification?

OSHA's rule does not ask for a card. It asks for a person who meets its definitions of competent and qualified. A competent person can identify existing and predictable hazards and has the authority to correct them promptly. A qualified person has a recognized degree, certificate or professional standing, or extensive knowledge, training and experience, and has shown the ability to solve the problems involved.

The employer decides who meets that. Training and testing are a common way to show it. The questions above come from an A/D director question set in the Crane Exam Prep bank.

FAQ

A/D director questions

What is an A/D director?
The person OSHA requires to direct crane assembly and disassembly. The term applies to whoever meets the rule's requirements for the job, regardless of title.
Who can be an assembly/disassembly director?
A person who meets OSHA's criteria for both a competent person and a qualified person, or a competent person who is assisted by one or more qualified persons.
Does the A/D director have to brief the crew?
Yes. Before starting, the A/D director must make sure the crew understands their tasks, the hazards and the positions to avoid, and must do it again when tasks change or people are added.
Who has to do the rigging during crane assembly?
A qualified rigger. 1926.1404(r) requires it for rigging work during assembly and disassembly.
Does OSHA require A/D director certification?
No. OSHA requires the person to meet its competent person and qualified person criteria. It does not require a certification card for the role.
Are these real exam questions?
No. They are original practice questions written from the OSHA rules and ASME B30 standards that crane exams draw on. OECP does not release its questions, and this site is not affiliated with OECP or the IUOE.

Keep going

One free practice test shows you where you stand.

25 questions. No sign-up. Every answer explained.

Start the free practice test
More practice questionsFree account, no card
Open the app