OECP tower crane

OECP tower crane certification

Tower crane is its own OECP certification, with its own written exam and practical. The entry bar is higher than for mobile cranes, because half of your documented hours have to be on tower cranes.

The short answer

You need 1,000 documented hours in the past five years, 500 of them on tower cranes. The written is 75 questions in two hours. The practical has six tests on a crane with a cab at least 40 feet above the ground, and you need 70 of 100 points. The card lasts five years.

Checked November 2026 against the OECP Crane Operator Candidate Manual (2025 edition), the OECP eligibility page and the NCCCO Foundation directory of accredited certification programs, June 29, 2026.

Tower crane certification at a glance

OECP tower crane operator
Who can applyIUOE members in good standing
Hours1,000 documented hours of crane-related experience or training in the past five years, 500 of them on tower cranes
Also requiredA current DOT or state medical card and a negative drug test dated within 90 days of the application
Crane types coveredTower cranes, including portable and self-erecting types
Written exam75 multiple-choice questions, two hours, no calculators
Written domainsPre-operations about 46%, operations about 44%, technical about 10%
Passing score500 on a scale of 200 to 800
PracticalSix tests. Start at 100 points, 70 passes
AccreditationNCCA, through November 30, 2029

Sources: OECP Crane Operator Candidate Manual, OECP initial certification eligibility and the NCCCO Foundation directory of accredited certification programs, June 29, 2026.

8 practice questions on tower cranes

Pick an answer to see whether you are right and why. These are original practice questions from the Crane Exam Prep question bank, not actual exam questions.

  1. Tower Crane

    1. What is required of tower crane operator control markings?

    Show answer

    Answer: C. Controls must be plainly marked to show their function and must move the crane in the direction indicated. Controls must be clearly marked to show function and must move the crane in the marked direction.

  2. Tower Crane

    2. Why must the manufacturer be consulted before mounting signs or advertisement boards on a tower crane?

    Show answer

    Answer: A. Added sail area may impair the ability of the crane to weathervane. Adding signage can affect the ability of the crane to weathervane out of service, so the manufacturer must be consulted before installing any of it.

  3. Tower Crane Test

    3. According to ASME B30.3, when working near power lines where should caution stickers be installed?

    Show answer

    Answer: D. At operators station and at the base of the crane. ASME B30.3 3-3.4.3-1(f): caution signs at the operator's station and at the base of the crane.

  4. Tower — Ropes & Hooks

    4. On a saddle-jib or luffing tower crane, what supports the jib?

    Show answer

    Answer: B. Pendant lines. The jib on saddle-jib and luffing cranes is supported by pendant lines running to the tower top or mast.

  5. Tower Crane

    5. On a fixed (top-slewing) tower crane, where is the slewing ring located?

    Show answer

    Answer: D. Just beneath the jib at the top of the tower. On a fixed-tower crane the tower itself does not turn; the slewing ring sits beneath the jib so only the upper works rotate.

  6. Tower — Operations

    6. When two tower cranes operate within reach of each other, what is the preferred way to prevent a collision?

    Show answer

    Answer: B. Keep the operators in constant radio contact, with one person organizing the loads and hoisting. For overlapping cranes the two operators should be in constant radio contact, with one person organizing the loads and hoisting so there are no collisions or fouled loads.

  7. Tower Crane Test

    7. According to ASME B30.3, Load Limit Device settings shall be verified by means of a static test using test loads of ___ of applicable rating.

    Show answer

    Answer: A. Specified by crane manufacturer. ASME B30.3 3-2.2.2: load limit device static test loads are as specified by the crane manufacturer.

  8. Operations

    8. According to ASME B30.3, what is the duration of a proof test?

    Show answer

    Answer: B. 5 minutes. ASME B30.3 3-3.2.2(c): proof test load held for 5 minutes.

Free OECP practice test

25 questions, no sign-up, every answer explained.

Start now

The tower crane practical

The manual requires a crane with an operating cab at least 40 feet above the ground.

Tower crane practical tests in the 2025 manual
TestTime limit
Pre-operational check2 minutes
Hand signalsAt least four ASME B30.3 signals
Start and stop circle, at a 50-foot hook height3.5 minutes
S-shaped corridor, forward and reverse3.5 minutes each way
S-shaped corridor, start circle to start circle2.75 minutes
Shutdown2 minutes

Source: OECP Crane Operator Candidate Manual, tower crane practical examination.

What to study for the tower crane written

Pre-operations is the biggest domain, at about 46% of the questions. That points at erection, climbing and inspection, not just running the crane. Start here:

Then test yourself. Take the free 20-question tower crane practice test.

FAQ

OECP tower crane questions

How many hours do I need for OECP tower crane certification?
1,000 documented hours of crane-related experience or training in the past five years, and 500 of them must be on tower cranes.
What is on the OECP tower crane practical?
Six tests: a pre-operational check, hand signals, a start and stop circle at a 50-foot hook height, an S-shaped corridor forward and in reverse, a corridor run from start circle to start circle, and shutdown.
Does OECP tower crane certification cover self-erecting cranes?
Yes. OECP lists the tower crane type as including portable and self-erecting cranes.
Is the tower crane written different from the mobile crane written?
Yes. It is a separate 75-question exam with its own domains: pre-operations about 46%, operations about 44% and technical about 10%.
Are these real exam questions?
No. They are original practice questions written from the OSHA rules and ASME B30 standards that crane exams draw on. OECP does not release its questions, and this site is not affiliated with OECP or the IUOE.

Keep going

One free practice test shows you where you stand.

25 questions. No sign-up. Every answer explained.

Start the free practice test
More practice questionsFree account, no card
Open the app