Rigging hardware: shackles, hooks, eyebolts and clips

The sling gets the attention, but the load goes through every piece of hardware between the hook and the lifting point. Each piece has a rating and a right way to load it.

The short answer

Rigging hardware is the detachable gear that connects slings to loads and hooks: shackles, links, rings, swivels, turnbuckles, eyebolts, hoist rings, wire rope clips, wedge sockets and rigging blocks. ASME B30.26 is the standard for it. OSHA requires shackles to stay within their marked working load limit, and wire rope clips to go on with the U-bolt on the dead end.

Checked November 2026 against the Mazzella reference guide to the ASME B30 standards and the text of OSHA 29 CFR 1926.251.

What ASME B30.26 covers

Hardware groups in ASME B30.26
GroupHardware
ShacklesAnchor and chain shackles, screw pin and bolt type
Adjustable hardwareTurnbuckles, eyebolts, eye nuts and swivel hoist rings
Compression hardwareWire rope clips and wedge sockets
Links, rings and swivelsIncluding master links and master link subassemblies
Rigging blocksSnatch blocks and other blocks used in rigging
Load indicating devicesDetachable devices that show the load

Source: Mazzella reference guide to the ASME B30 standards.

Hooks have their own volume, B30.10. Slings are in B30.9, and lifters and clamps in B30.20.

8 practice questions on rigging hardware

Pick an answer to see whether you are right and why. These are original practice questions from the Crane Exam Prep question bank, not actual exam questions.

  1. Rigging Hardware

    1. Which type of eye bolt must be used for angular (side) lifts?

    Show answer

    Answer: B. Shoulder type eye bolts. Regular (plain) eye bolts must never be used for angular lifts; only shoulder-type (or machinery) eye bolts, properly seated, may be loaded at an angle.

  2. Rigging Hardware

    2. In a wedge socket, the live (loaded) end of the wire rope must be…

    Show answer

    Answer: C. In alignment with the socket's pin. The live end of the rope in the wedge socket cavity must line up with the socket pin so the load pulls straight.

  3. Rigging Hardware

    3. Where is the first wire rope clip installed when making an end termination?

    Show answer

    Answer: D. One base width from the dead end of the rope. The first clip is applied one base width from the dead end; the second clip goes as near the loop or thimble as possible.

  4. Rigging Hardware

    4. A "shackle" is best defined as:

    Show answer

    Answer: A. A U-shaped connecting device consisting of a body (bow or dee) closed by a removable pin, used to connect rigging components. A shackle is a U-shaped load-bearing connector with a pin across its opening (screw pin, bolt-type, or round pin). Anchor (bow) and chain (dee) patterns are the common body styles.

  5. Rigging Hardware

    5. A wedge socket is installed correctly when:

    Show answer

    Answer: C. The live load line pulls in a straight line from the socket pin, with the dead end offset. The wedge tightens only when the load line pulls straight past the pin. Installed backwards, the wedge is driven loose and the rope pulls out. Note also that non-rotating rope is not ideal in a wedge socket because of core slippage.

  6. Rigging Hardware

    6. According to the shackle side-loading reduction chart for screw pin and bolt type shackles, what is the adjusted working load limit at 45 degrees and at 90 degrees from in-line?

    Show answer

    Answer: A. 70% at 45 degrees; 50% at 90 degrees. Side loading reduction: 0 deg (in-line) = 100%, 45 deg = 70%, 90 deg = 50% of rated working load limit. Angle loads must be applied in the plane of the bow, and round pin shackles must never be side loaded.

  7. Rigging Hardware

    7. In what orientation must the load always be applied to an eye bolt?

    Show answer

    Answer: A. In the plane of the eye, not at an angle to it. Load must always be applied in the plane of the eye — never at an angle across it — to avoid bending the eye.

  8. Rigging Hardware

    8. When installing U-bolt wire rope clips, the U-bolt section must be placed on which part of the rope?

    Show answer

    Answer: A. On the dead end, with the live (load-carrying) end resting in the saddle. The U-bolt always goes over the dead end of the rope; the live end rests in the saddle. The first clip goes one base width from the dead end.

Free OECP practice test

25 questions, no sign-up, every answer explained.

Start now

OSHA's rules for hardware in construction

From 29 CFR 1926.251
ShacklesNot loaded beyond the working load limit marked on them
HooksUsed within the manufacturer's recommended safe working loads
Hooks with no manufacturer ratingTested to twice the intended safe working load before first use, with a record kept
Chain sling attachmentsHooks, rings, links and other attachments must have a rated capacity at least equal to that of the chain
Makeshift hardwareJob or shop hooks and links, and makeshift fasteners formed from bolts or rods, are not used
Wire rope sling eyesNot formed with wire rope clips or knots
Web sling fittingsBreaking strength at least equal to the sling, and free of sharp edges that could damage the webbing

Source: OSHA 29 CFR 1926.251.

Wire rope clips: OSHA's table

When U-bolt clips form an eye, OSHA sets the number and spacing by rope size. The U of the clip goes on the dead end of the rope, and the saddle on the live end.

Number and spacing of U-bolt wire rope clips, 29 CFR 1926.251 Table H-2
Rope diameterDrop-forged clipsMinimum spacing
1/2 inch33 inches
5/8 inch33 3/4 inches
3/4 inch44 1/2 inches
7/8 inch45 1/4 inches
1 inch56 inches
1 1/8 inch66 3/4 inches
1 1/4 inch67 1/2 inches
1 3/8 inch78 1/4 inches
1 1/2 inch79 inches

Source: OSHA 29 CFR 1926.251, Table H-2.

Spacing works out to six rope diameters. Clips can form an eye in other wire rope, but OSHA does not allow them to form the eye of a sling, bridle or bull wire.

Good habits the questions test

  • Load a shackle in line. Side loading reduces its working load limit.
  • Use shoulder eyebolts for angled pulls, and keep the load in the plane of the eye.
  • Seat the wedge socket the right way. The live line pulls straight from the pin.
  • Read the marking. No legible rating, no lift. OSHA says rigging equipment without legible markings is not used.
  • Match the weakest link. The assembly is only rated as high as its lowest-rated part.

Take the 15-question rigger test for more.

FAQ

Rigging hardware questions

What is rigging hardware?
The detachable gear that connects slings to loads and to the hook: shackles, links, rings, swivels, turnbuckles, eyebolts, hoist rings, wire rope clips, wedge sockets and rigging blocks.
Which standard covers rigging hardware?
ASME B30.26. Hooks are covered by ASME B30.10 and slings by ASME B30.9.
How many wire rope clips do I need?
OSHA's Table H-2 sets the number by rope size when clips form an eye: three drop-forged clips for 1/2 inch rope, four for 3/4 inch and five for 1 inch.
Which way do wire rope clips go on?
With the U-bolt on the dead end of the rope and the saddle on the live end.
Can I use a homemade hook or link?
No. OSHA's construction rule prohibits job or shop hooks and links and makeshift fasteners formed from bolts or rods. A hook with no manufacturer rating must be tested to twice its intended safe working load before first use.
Are these real exam questions?
No. They are original practice questions written from the OSHA rules and ASME B30 standards that crane exams draw on. OECP does not release its questions, and this site is not affiliated with OECP or the IUOE.

Keep going

One free practice test shows you where you stand.

25 questions. No sign-up. Every answer explained.

Start the free practice test
More practice questionsFree account, no card
Open the app